INDUSTRIAL HUMIDITY CONTROL / SINCE 2004 Talk to a specialist 765-702-4083
IHCIndustrial
Humidity Control LLC
HOW TO CALCULATE LOAD

Electronics Load Calculator Guide

Humidity load planning for electronics manufacturing facilities.

Industrial Humidity Control · IHC-LCGE v1.0 · 08.29.2026 · Updated 2026-11-04

Industry & humidity target

Start with the material or process requirement.

Choose the indoor conditions

The example uses 40% RH at 72°F. Treat that as a sizing scenario, not a universal electronics or cleanroom requirement. The facility’s ESD program, moisture-sensitive devices, process specifications and environmental controls determine the acceptable range.

RH can affect how quickly surface charge dissipates. It complements grounding, ionization, ESD-safe handling and packaging; a humidity set point alone does not establish an effective ESD program.

Moisture-sensitive devices have package-specific exposure and storage requirements. Preserve the manufacturer’s floor-life and packaging controls when setting room conditions.

The reference treats reflow, soldering, cleaning and flux extraction as fully exhausted. Verify the actual plant arrangement and count the full outdoor discharge; do not apply a woodworking dust-collection loss fraction.

Source reference · page 3 (PDF)

What the calculation represents

Cold outdoor air contains relatively little water vapor. Heating it lowers its relative humidity without itself removing water. Replacing plant air with that winter air creates the humidification load.

Atomization creates small droplets; airflow carries them into open space where they evaporate. Dalton’s law describes vapor’s partial pressure, diffusion follows concentration gradients, and temperature affects saturation pressure. Airflow and mixing determine distribution; there is no universal fixed speed for vapor diffusion.

Source reference · page 4 (PDF)

Building & air balance

Find the outdoor-air exchange that governs the winter load.

Collect the building data

Collect the building data
InputWhere to obtain it
Dimensions and served zonesPlans and measured areas/heights; multiply length × width × height.
Outdoor design temperatureProject design conditions for the location.
Indoor temperature and RHMaterial and process requirements.
Exhaust CFMFans, dust collection and process extraction; distinguish outdoor discharge from return air.
Makeup-air CFMMAUs, rooftop units and actual outdoor-air fractions.
Operating modesProduction schedule, door openings, economizer minimum and freeze protection.
Secondary moisture loadsProduct regain, process evaporation and occupancy when material.

Source reference · page 6 (PDF)

Use the governing airflow once

Do not add exhaust and makeup air together as though they were independent losses. The practical method uses the larger value to represent replacement-air demand.

If measured CFM is unavailable, estimate outdoor-air exchange from building volume and an explicit ACH assumption. The source’s screening values are 1 ACH for a tight building, 1.5 for average conditions and 2 for a loose building. Replace estimates with verified air-balance data when possible.

Avoid using total HVAC supply or recirculating cleanroom airflow as outdoor exchange. Confirm each stream’s actual destination and operating condition.

Governing CFM = greater of total outdoor exhaust CFM and total makeup-air CFM

Source reference · page 5 (PDF)

Economizers and multiple HVAC units

The source uses roughly 400 CFM per ton as an initial comfort-HVAC estimate, with a typical 350–450 range. Actual fan data, a test-and-balance report and BAS trends are preferable.

Example: 100 tons × 400 × 0.20 = 8,000 CFM of outdoor air. For three 50-ton units at 15%, 20% and 20%, calculate each separately: 3,000 + 4,000 + 4,000 = 11,000 CFM.

Confirm winter damper settings and low-temperature lockouts against the design-day condition. Do not assume a 20% minimum or zero outside air without checking the actual sequence. Classified process air systems require their own design data.

Estimated outdoor CFM = unit tons × estimated supply CFM/ton × actual outdoor-air fraction

Source reference · page 19 (PDF)

Process-specific verification

For a classified cleanroom, use the designed outdoor/makeup air and exhaust flows from its mechanical documents. Total recirculating cleanroom ACH is not the same as outdoor-air replacement.

Check relevant process-tool exhaust and treatment requirements with the process and EHS teams. Airflow values should reflect actual operating modes.

Confirm room targets against the facility’s ESD and moisture-sensitive-device procedures; the guide is not a substitute for those controls.

Source reference · page 21 (PDF)

Moisture & calculation

Convert the target conditions and outdoor-air volume to pounds per hour.

Selected saturation values

These are selected values from the source’s Table 2-A, sufficient for its worked examples and common indoor temperatures. Use the original table for other listed temperatures or obtain appropriate psychrometric data.

The units here are grains per cubic foot. Do not substitute a chart value expressed in grains per pound of dry air. One pound of water equals 7,000 grains.

Selected saturation values
Temperature · °FWater vapor at 100% RH · grains/ft³
−100.29
−50.35
00.48
50.61
100.70
150.99
201.24
251.56
301.95
352.38
402.86
453.44
504.11
554.89
605.80
656.85
667.07
677.31
687.57
697.80
708.10
718.32
728.59
738.87
749.15
759.45
8011.04

Source reference · page 7 (PDF)

Calculate the moisture deficit

  1. Multiply saturation grains/ft³ at the indoor temperature by the target RH expressed as a decimal.
  2. For the source’s practical design method, multiply saturation grains/ft³ at the outdoor design temperature by 0.50.
  3. Subtract the outdoor allowance from the indoor target to obtain the deficit.

Source reference · page 7 (PDF)

CFM and ACH formulas

The CFM formula converts minutes to hours. The ACH alternative already gives an hourly air volume, so it does not multiply by 60 again.

The source uses a 15% margin. Any larger allowance for door traffic, uncertainty or expansion should be an explicit design decision. Preserve calculation precision until the final selection; small differences from rounded source examples are expected.

Load (lb/hr) = deficit (grains/ft³) × governing CFM × 60 ÷ 7,000 ACH alternative = deficit × building volume (ft³) × ACH ÷ 7,000 Final capacity = load × 1.15

Source reference · page 8 (PDF)

When to use the comprehensive method

Do not assume secondary factors cancel or assign a universal percentage. Estimate them from the actual process before changing equipment capacity.

When to use the comprehensive method
FactorEffect
Product regainDry incoming stock absorbing moisture adds to demand.
Process water vaporDocumented moisture released into the served space can reduce humidifier demand.
OccupancyMoisture from people may reduce the net demand.
Unusual operational changesHigh throughput, frequent doors or tight tolerances warrant a more detailed balance.

Source reference · page 10 (PDF)

Worked example & equipment

Follow the source’s illustrative facility from inputs to equipment selection.

Worked example: 1,419 lb/hr

This is the guide’s sizing example, not a customer project or a recommendation for every facility in the industry.

Worked example: 1,419 lb/hr
StepValue / calculation
Building400 × 250 × 20 ft = 2,000,000 ft³; 100,000 ft²
Exhaust / makeup air40,000 / 45,000 CFM
Governing airflow45,000 CFM
Indoor target40% RH at 72°F
Saturation at indoor temperature8.59 grains/ft³
Indoor target moisture8.59 × 0.40 ≈ 3.44 grains/ft³ (source rounding)
Outdoor design0°F; 0.48 grains/ft³ at saturation
Outdoor moisture allowance0.48 × 0.50 = 0.24 grains/ft³
Moisture deficit3.44 − 0.24 = 3.20 grains/ft³
Hourly air volume45,000 × 60 = 2,700,000 ft³/hr
Base load3.20 × 2,700,000 ÷ 7,000 ≈ 1,234 lb/hr
Capacity with 15% marginApproximately 1,419 lb/hr, following source rounding
Water equivalentApproximately 2.84 gpm

Source reference · page 9 (PDF)

Translate capacity into fans and pumps

A 27-inch ring with fourteen 7.94 lb/hr blue-band nozzles supplies 111.16 lb/hr at the stated pressure. Recalculate if the nozzle size or count changes.

  • Thirteen fans with fourteen 7.94 lb/hr nozzles each: 13 × 111.16 = 1,445.08 lb/hr.
  • The example uses two 1.75 gpm stations, 3.5 gpm total. Confirm the zones, nozzle demand, treatment and pump bypass capacity.
  • Provide thirteen rings/valves, 182 nozzles and matched controls and distribution. Confirm the suitability of open-space fan mist for the actual production environment.

Source reference · page 12 (PDF)

Sizing worksheet and bill of materials

In a spreadsheet, calculate governing CFM as MAX(exhaust cell, makeup-air cell). Keep it in a separate cell; do not include the result cell inside its own MAX formula.

Useful conversions: CFM × 60 = ft³/hr; 1 gallon ≈ 8.34 lb of water; 1 gpm ≈ 500.4 lb/hr; °C = (°F − 32) ÷ 1.8. Send the completed inputs to IHC for the final layout and equipment selection.

Sizing worksheet and bill of materials
RecordRequired value
BuildingDimensions, volume and served zones
Design conditionsOutdoor temperature; indoor temperature and RH
Air balanceExhaust, makeup air, governing CFM or documented ACH
MoistureIndoor target, outdoor allowance and deficit
CapacityCalculated load, chosen margin and final lb/hr / gpm
EquipmentFan count, nozzle size/count, ring output and airflow ratio
Pump selectionStation flow, zone split and pump bypass capacity
InstallationRelays, tubing, fittings, supports, filtration, treatment and drain
VerificationSource of each input, date and responsible reviewer

Source reference · page 15 (PDF)

Parts & references

Continue with related guides, parts and the original PDF.

Original & related PDFs

This web guide is adapted from the IHC reference linked below. The original PDF retains its diagrams, document revision and printable layout.

Need help with your system?

Talk through your facility or an existing system with IHC.

Contact IHC